Started on the kitchen renovation. Removed all cupboard contents and packed them away in p
lastic/cardboard boxes. Took down wooden shelves, pine cladding on ceiling and wall cabinets and fitted one double wall unit in laundry room to help convert this room into a temporary kitchen.
11/03/2009
Alno kitchen workmen arrived to remove the remainder of kitchen and replace ceiling which was damaged when
I originally put up pine cladding. They also altered plumbing and electrics to suit new kitchen.
13/03/2009
Plasterer arrived today to plaster new Giprock plasterboard ceiling and make good walls.
16/03/2009
Plaster dry enough
to paint so gave walls and ceiling two coats of white emulsion and Bob , my son, prepared and put one coat of gloss on the woodwork.